Kirkland Project Updates:

Western Land and Ranches Local Development Liaison – Axel Buchwalter – abuchwalter@clarkhill.com

SEPTEMBER 2022

WLR sent an inquiry on the MLS Listing for Rancho Santa Ynez

APRIL 2023

WLR performed Property visit

WLR began Preliminary Business Plan Developed

WLR began negotiations with the Seller

MAY 2023

WLR Placed Property in Escrow – May 15, 2023

JUNE 2023

WLR Met with Yavapai County District 1 Supervisor Harry Oberg to discuss prelim plan (1800 acres/ 720 lots)

WLR Submitted Letter of intent Yavapai County with revised project plan to include 400-600 lots

WLR attended the Kirkland Project Pre-Application Meeting with Yavapai County– June 6, 2023

WLR Engages in Kirkland Project Development Due Diligence. Civil Engineering, Hydrology, Municipalities, Safety.

JULY 2023

WLR Contracted Matrix New World to perform Water Study, Well Analysis, and Tech Memo

SEPTEMBER 2023

WLR launces Santa Ynez Project Website – Sept 27, 2023

OCTOBER 2023

WLR hosts Kirkland Project Citizen Participation Meeting – October 3, 2023, at the Sonrise Fellowship Church 8530 Walden Blvd, Kirkland, AZ 8332.

Based on Community Input, WLR reduced the original size of the project from 1,800 acres (760 lots) to 764 acres (262 lots). This was accomplished through a negotiated sale of 1,100 acres to a local rancher.

NOVEBER 2023

Kirkland Project Sketch Plan – WLR submitted amended Sketch Plan to Yavapai County based on community feedback, and updated project scope to Yavapai County – November 6, 2023.

Kirkland Project Sketch Plan – WLR attended technical review with Yavapai County – November 30, 2023.

WLR continues the Kirkland Project Development Due Diligence through the first quarter of 2024 in preparation to submit Preliminary Plat to Yavapai County.

 

DECEMBER 2023 – SEPTEMBER 2024

WLR Contracted Lee Engineering (PHX, AZ) to complete Traffic Analysis Impact (TIA)

WLR Contracted Matrix New World Engineering, Inc. (Prescott, AZ) to perform Well Draw Downs

WLR Contracted Lyon Engineering (Prescott, AZ) to engage in discussions related to on-and-offsite improvements, and Draft the Preliminary Plat

WLR Contracted Prescott Environmental (Prescott, AZ) January 2024

Prescott Environmental completed Pec Tests (25% of all lots, 3 holes per lot) and Environmental Studies

WLR aligned with Yavapai County Environmental Services to initiate the counties’ required Studies.

WLR engaged in ongoing discussions with Yavapai County Public Safety Services regarding Fire Protection, and Emergency Management Services

WLR engaged ADOT to begin discussions regarding the improvements needed at Kirkland Junction

WLR assembled an Internal Team to address Public Comment, and Comments and Requirements from Yavapai County.

WLR continued communication with all Yavapai County Departments in an effort to meet all requirements set forth to date.

WLR attends the Yavapai County Planning and Zoning Meeting – Preliminary Plat Approval Meeting. 10.3.2024

NOVEMBER 2024

WLR attends Yavapai County Board of Supervisors Meeting – Preliminary Plat Approval Meeting 11.06.2024 – Project remanded back to Yavapai County Planning and Zoning.

FEBRUARY 2025

WLR submitted updated Preliminary Plat to Yavapai County Planning and Zoning for Review 2.05.2025

WLR addressed Review Comments related to the Preliminary Plat Submittal on 2.5.24

WLR adjusted Street Names based on new Plat

WLR received Sanitary Certificate of Approval for the new Plat from Yavapai County Environmental Unit

WLR hosted the 1st Stakeholder and 2nd Citizen Participation Meeting on 2.20.25 at the Sonrise Fellowship Church 8530 Walden Blvd, Kirkland, AZ 8332.

WLR Contracted Williamson Valley Fire District for Fire Protection and Emergency Services

MAY 2025

WLR attends the Yavapai County Planning and Zoning meeting, May 8, 2025. – 4-4 Neutral Vote – Project moved to Board of Supervisors

WLR engaged with Yavapai County Development Services to discuss Open Space Possibilities further.

JULY 2025

Yavapai County Board of Supervisors meeting, July 2, 2025.

Thank you for your time and interest.  Please continue to follow our website for project updates.